The hotel could never take more than eleven rooms out of service at once. Each stage had to be fully handover-ready within five days.
Free delivery from €750.00 · Professional installation across NRW
Hotel · Düsseldorf
Room furnishing for 42 hotel rooms plus the lobby — delivered and installed in four stages during ongoing operation.

Brief
The hotel could never take more than eleven rooms out of service at once. Each stage had to be fully handover-ready within five days.
Solution
Pre-picking in our warehouse: every room was packed and labelled as a finished set. The fitters completed three rooms per day.
Services
Gallery



B2B terms availableCurved brass wall light with a swivelling arm.
incl. VAT, plus shipping
Professional installation
B2B terms availableRound mirror with a slim brass frame, 90 cm diameter.
incl. VAT, plus shipping
Professional installation
B2B terms availableTable lamp with a ceramic base and fabric shade, dimmable.
incl. VAT, plus shipping

Upholstered bench on an oak frame, 160 cm.
incl. VAT, plus shipping
Tell us about it — we will prepare an individual quotation.
Next project
OfficeA reception and three meeting rooms focused on confidentiality and acoustics.